Kitchen Remodel Timeline: What Actually Happens Each Week

— by Apollo Brothers.

Cabinets and countertops set your schedule. Here's the realistic week-by-week.

April 28, 2026 7 min read

The two questions every kitchen client asks are 'how much' and 'how long.' The honest answer on timing is 6-10 weeks on site, but the clock really starts when you order cabinets.

Weeks 1-2: Demo and rough-in

Cabinets and appliances out, walls opened where needed, plumbing and electrical relocated, and inspections scheduled. This is the loudest, dustiest phase and it moves fast.

Weeks 3-4: Close-up and prep

Insulation, drywall, taping, priming, and flooring if it runs under the cabinets. Nothing looks like progress but everything depends on it.

Weeks 5-6: Cabinet installation

Boxes get set, leveled, and scribed to the walls. Once cabinets are in, the countertop fabricator can template — and templating is the hard gate in every kitchen schedule.

Weeks 7-8: Counters, backsplash, finish

Counters typically take 7-14 days from template to install. Then backsplash tile, plumbing hookups, appliance install, trim, and paint touch-up.

What causes delays

Two things: cabinet lead times (order 8-12 weeks ahead) and change orders mid-project. Deciding to move the sink after rough-in adds a week and real money. Lock the layout before demo.

Frequently asked questions

Can I use my kitchen during the remodel?
No, but we help set up a temporary kitchen with the fridge, microwave, and a sink nearby.
When should I order cabinets?
As early as possible — semi-custom lines commonly run 8-12 weeks.

Related services

— Free, no-pressure estimate

Let's build something
worth keeping.

Tell us what you're planning — a roof, a kitchen, an addition, a leak at midnight. We answer the phone, and we show up when we say we will.

Open 24/7 · Licensed & Insured · BBB Accredited
Call Now Free Quote